Steps for horizontal installation of grid Bridges

Jul 05, 2019

Leave a message

Basic steps for horizontal installation of grid Bridges:

1. The grid bridge and its bracket and the metal cable conduit introduced or drawn out must be reliably grounded or zero-connected, and the whole length and its bracket shall be connected with the grounding or zero-connected main line at no less than 2 places;

2. The two ends of the connection plate between non-galvanized grids and Bridges shall be bonded with the copper core grounding wire. The minimum allowable load area of the grounding wire shall not be less than 4mm;

3. When the design is not required, the spacing of the brackets for horizontal installation of the bridge is 1.5~3m; The spacing of vertically mounted supports shall not be greater than 2m. If from the ceiling construction with expansion screw fixed rebar fixed ~ from the wall construction to use the Angle frame fixed;

4. The two ends of the connecting plate between galvanized Bridges shall not be bonded to the ground wire, but the two ends of the connecting plate shall be no less than 2 connection fixing bolts with anti-loosening nuts or anti-loosening washers.